Question: Question 2 : [ 3 0 Marks ] line, givent is introducing a new model of a sweater and needs to balance the process for

Question 2: [30 Marks]
line, givent is introducing a new model of a sweater and needs to balance the process for its new production
the cycle the following task times, precedence relationships and precedence diagram as below. Assume that
\table[[Task,Time (minutes),Immediate Predecessor],[A,8,Nil],[B,7,Nil],[C,4,A, B],[D,6,A],[E,6,D, C],[F,6,C],[G,4,D, F],[H,6,E, G],[,,]]
You are required to:
a. Calculate the minimum possible number of workstations (Nmin) required for this production process.
b. Assign tasks to stations by using the greatest number of followers decision rule. the longest task time as the tie breaker to assign tasks to stations.
c. Draw the product layout with the
d. Determine the layout with the assignment of task into each workstation.
[12 Marks]
e. Compute the efficiency of the process.
[3 Marks]
[3 Marks]
for this production line assuming a 600-minute working day. [3 Marks]
produs the designed product layout and the operating time unchanged, LN wishes to improve the daily target? Yivity and the efficiency both by 3% without any additional cost, how should LN do to achieve the [6 Marks]
End of the assignment
 Question 2: [30 Marks] line, givent is introducing a new model

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!