Question: Question 2 : [ 3 0 Marks ] line, givent is introducing a new model of a sweater and needs to balance the process for
Question : Marks
line, givent is introducing a new model of a sweater and needs to balance the process for its new production
the cycle the following task times, precedence relationships and precedence diagram as below. Assume that
tableTaskTime minutesImmediate PredecessorANilBNilCA BDAED CFCGD FHE G
You are required to:
a Calculate the minimum possible number of workstations required for this production process.
b Assign tasks to stations by using the greatest number of followers decision rule. the longest task time as the tie breaker to assign tasks to stations.
c Draw the product layout with the
d Determine the layout with the assignment of task into each workstation.
Marks
e Compute the efficiency of the process.
Marks
Marks
for this production line assuming a minute working day. Marks
produs the designed product layout and the operating time unchanged, LN wishes to improve the daily target? Yivity and the efficiency both by without any additional cost, how should LN do to achieve the Marks
End of the assignment
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock