Question: QUESTION 2 : ( 3 0 points ) A planner identified for a certain project the activities listed in the table below and their precedence

QUESTION 2: (30 points)
A planner identified for a certain project the activities listed in the table below and their precedence relationships as well as their durations. (Note: All relations are FS)
\table[[Activity,Predecessor(s),Duration (days),Activity,Predecessor(s),Duration (days)],[A,B C,5,I,F,9],[B,-,3,J,H,12],[C,-,4,K,I, J,6],[D,B,2,L,D, E, G,10],[E,A,4,M,K,7],[F,C,7,N,L,M,8],[G,F,8,O,-,5],[H,C,6,P,-,8]]
It is required to:
(a) Draw the AON network of the project (follow the sequence step).
(b) Calculate and show on the network the ES, EF, LS, LF, TF , and FF values of each activity.
(c) Identify the project's critical path and show it on the network.
(d) Determine the project duration.
QUESTION 2 : ( 3 0 points ) A planner identified

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!