Question: QUESTION 2 : ( 3 0 points ) A planner identified for a certain project the activities listed in the table below and their precedence
QUESTION : points
A planner identified for a certain project the activities listed in the table below and their precedence relationships as well as their durations. Note: All relations are FS
tableActivityPredecessorsDuration daysActivity,PredecessorsDuration daysAB CI,FBJHCKI, JDBLD E GEAMKFCNLMGFOHCP
It is required to:
a Draw the AON network of the project follow the sequence step
b Calculate and show on the network the ES EF LS LF TF and FF values of each activity.
c Identify the project's critical path and show it on the network.
d Determine the project duration.