Question: QUESTION 2 3 4 4 B A 8 7 Start E E F End 5 4 D 6 . G Put an asterisk (*) next

QUESTION 2 3 4 4 B A 8 7 Start E E F End 5 4 D 6

QUESTION 2 3 4 4 B A 8 7 Start E E F End 5 4 D 6 . G Put an asterisk (*) next to the critical path. Using the network diagram above, you are required to: (a) Find the number total number of paths and calculate their respective durations. (3 marks) (b) Find the critical path. (2 marks) (c) Calculate the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS) and Latest Finish (LF). (15 marks) [Total 20 marks]