Question: QUESTION 2 ( 3 5 ) 2 . 1 . You have been appointed by your local government to design preliminarily a dam at the

QUESTION 2
(35)
2.1. You have been appointed by your local government to design preliminarily a dam
at the outlet of the quaternary catchment having the highest net area in D12 of the
Orange drainage system. The design is based on the data provided in the Water
Resources of 1990(WR90) reports as follows:
-The live storage (10106m3) is based on a recurrence interval of 50 years low flow
sequence with an allowance of 25% for sediment accumulation.
The region applies strictly to catchment areas between 0 and 1400km2. Consider
medium category (for sediment accumulation)
Use 0.05 significance level for sedimentation yield.|
Calculate:
a. The gross draft (in Mm3a) to be met
b. Sediment rate (t/a)
c. Trap efficiency (%)
d. Average silting rate (t/a)
e. Total dam capacity (Mm3)
(57=35)
QUESTION 2 ( 3 5 ) 2 . 1 . You have been

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!