Question: QUESTION 2 3 Table of Crashing Decision table [ [ , TIME ( WEEKS ) , COST ( $ ) ] , [ ACTIVITY

QUESTION 23
Table of Crashing Decision
\table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,---,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]]
Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,
Using Table of Crashing Decision, what is the minimum time schedule for this project?
fewer than 8 weeks
8 weeks
9 weeks
more than 9 weeks
 QUESTION 23 Table of Crashing Decision \table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,---,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]] Since no

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!