Question: Question 2 4 ( 1 point ) The procurement procedure will be initiated by the project manager. What was supposed to be given to the
Question point
The procurement procedure will be initiated by the project manager. What was supposed to be given to the project manager prior to the process commencing?
Procurement Statement Of Work
Seller Proposal
Procurement Management Plan