Question: Question 2 4 3 . 0 3 pts ( Answers questions 2 4 - 2 8 ) Based on the following project network diagram, which

Question 24
3.03 pts
(Answers questions 24-28) Based on the following project network diagram, which provides activity precedence information and durations (in weeks), find the critical path.
A-B-E-G-H
A-C-E-G-F-H
A-B-D-F-H
A-C-D-F-H
A-C-E-G-H