Question: QUESTION 2 ( 5 0 Points ) Draw the logic diagram for the activities listed on the following table using only the activity on node

QUESTION 2(50 Points) Draw the logic diagram for the activities listed on the following table using only the activity on node notation. Indicate the early start (ES), late start (LS), early finish (EF), and late finish (LF) dates as well as the total floats and critical path. Make sure to properly identify the project activities based on the ID provided on the table. Show all your calculations.
\table[[ID,Activity Description,\table[[Duration],[(In Days)]],Predecessors],[1,Demolition,5,-],[2,Procure Ductwork,20,-],[3,Procure Doors,20,-],[4,Procure Light Fixtures,12,-],[5,Procure Hardware,15,-],[6,Install Stud Walls,5,1],[7,Rough-in Electrical,4,6],[8,Install Ductwork,5,2],[9,Install Drywall,5,7],[10,Tape & Finish Drywall,5,9],[11,Install Ceiling Supports,4,10],[12,Install Frames & Doors,5,3,10],[13,Finish Electrical,4,10],[14,Install Ceiling Tiles,2,11,8],[15,Install Light Fixtures,3,4,13],[16,Install Hardware,3,5,12],[17,Paint,5,16,14,15
QUESTION 2 ( 5 0 Points ) Draw the logic diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!