Question: Question 2 5 . A deliverable has passed internal quality control, but the customer refuses to accept it because the quality is not at the
Question A deliverable has passed internal quality control, but the customer refuses to accept it because the quality is not at the expected level. What will happen next?
The contract will be referred to the legal department.
Control Quality will be repeated.
Manage Quality will be repeated.
The project manager will facilitate further discussions with the customer.