Question: Question 2 6 : A project manager gets a call from a team member notifying him that there is a variance between the speed of

Question 26: A project manager gets a call from a team member notifying him that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, he is in which part of the project management process?
Options:
Monitoring and Controlling
Executing
Closing
Initiating