Question: Question 2 7 3 . 0 3 pts According to the Critical Path Method ( CPM ) , if you subtract the early finish from

Question 27
3.03 pts
According to the Critical Path Method (CPM), if you subtract the early finish from the late finish (i.e., LF-EF), the result is the activity's slack time.
True
False
 Question 27 3.03 pts According to the Critical Path Method (CPM),