Question: Question 2 : ( 7 Points ) A project consists of seven activities. The precedence relationships are given in the following table. a . Construct
Question : Points
A project consists of seven activities. The precedence relationships are given in the
following table.
a Construct a network for this project.
b Compute the earliest and the latest starting and finishing times for each activity and
identify the critical path.
c What group of activities will have to be completed by day in order to guarantee
that the project will not be delayed?