Question: Question 2 7 pts Find the net present value (NPV) for a proposed project costing $22,730. Assume that the appropriate cost of capital for projects

Question 2 7 pts Find the net present value (NPV) for a proposed project costing $22,730. Assume that the appropriate cost of capital for projects of this risk level, at this company is 15.12%, and the estimated cash flows for the life of the project are as follows: Year 1 Year 2 Year 3 Year 4 Year 5 $4,242 $3,744 $4,337 $11,690 $6,825