Question: QUESTION 2 7 Using Project Management CPM AON: What is the earliest possible finish for Activity U ? 2 3 3 1 1 9 2

QUESTION 27
Using Project Management CPM AON: What is the earliest possible finish for Activity U?
23
31
19
24
29
21
 QUESTION 27 Using Project Management CPM AON: What is the earliest