Question: Question 2 8 ( 2 points ) Listen Why is the meeting between alsproject stakeholders and key players scheduled as the final step in the

Question 28(2 points)
Listen
Why is the meeting between alsproject stakeholders and key players scheduled as the final step in the planning phase?
to give the client time to finalize their requirements for the project
so there is time to fine-tune the statement of work
the budgets and timelines need to be finalized before stakeholders and key players can understand the scope of the projects and their role within the project