Question: Question 2 9 ( 1 point ) A project is to design a complex mechanical part. The project team is spending time on improving project
Question point
A project is to design a complex mechanical part. The project team is spending time on improving project processes to increase quality and efficiency. This is considered:
Quality assurance
Both quality assurance and control
Quality Control
Neither quality assurance nor control