Question: Question 2 9 2 p t s A third method for determining the forecasted cost at completion is to re - estimate the costs for
Question
A third method for determining the forecasted cost at completion is to reestimate the costs for all the remaining work to be performed and then add this reestimate to the cumulative actual cost. If the amount of cumulated actual costs is less than difference between the total budgeted cost and the reestimate, then