Question: Question 2 9 3 . 0 3 pts According to the CPM and PERT project scheduling methods, activity slack Marks either the start or the
Question
pts
According to the CPM and PERT project scheduling methods, activity slack
Marks either the start or the completion time of a task
Is the amount of time a task may be delayed without changing the overall project completion time
Is a task or subproject that must be completed
Is the latest time an activity can be started without delaying the entire project
All of the above
Question
pts
Which of the following are elements of a typical Project Charter?
Resources
Scope
Risk management
Schedules
All of the above