Question: Question 2 A local major building contractor will utilize a total of 8 0 , 0 0 0 bags of sand for completing a new
Question
A local major building contractor will utilize a total of bags of sand for completing a
new private commercial building project with a contract period of years. In order to make
each order of sand, it will take one third of an hour of a purchasing staff at $ per hour of
wages, half of an hour of a technician with the salary of $ per hour, and $ for materials,
phone and mailing charges. The holding cost per average stock per year is $ It is also
assumed that the total working days for the project is days per year, and the lead time
between the placement of a new order and the receipt of the order is working days.
a On behalf of the contractor, recommend the best reorder policy based on the above
information and data by determining the: i optimal order quantity per order; ii
annual ordering cost; iii annual holding cost; iv total annual inventory cost; v
optimal number of orders that should be placed per year; and vi reorder point
ROP
b If the optimal order quantity is changed to bags, what would be the i ordering
cost for each order; and ii holding cost per bag per year, under the optimal order
policy?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock