Question: Question 2 Activity Predecessors Time ES EF LS LF A 7 12 B 8 A 13 20 D A 11 12 E B 14 17

Question 2 Activity Predecessors Time ES EF LS LFQuestion 2

Activity Predecessors Time ES EF LS LF A 7 12 B 8 A 13 20 D A 11 12 E B 14 17 F B 11 G D, E 6 H C 20 K F 29 L G, H, K 9 Refer to the above scenario. What is the earliest start time for activity H? O Week 14 Week 15 Week 16 O Week 17