Question: QUESTION 2 Actual Costs for a project so far are $50,000, and the Estimate to Complete is $50,000. If a project's Budget at Completion was

 QUESTION 2 Actual Costs for a project so far are $50,000,

QUESTION 2 Actual Costs for a project so far are $50,000, and the Estimate to Complete is $50,000. If a project's Budget at Completion was originally $120,000, what is the Variance at Completion