Question: Question 2. [Conduct Procurement, Vendor Selection] A project received proposals from a response to RFP and is in the decision process of selecting one vendor.
Question 2. [Conduct Procurement, Vendor Selection]
A project received proposals from a response to RFP and is in the decision process of selecting one vendor. The project selection committee agreed on the criteria and the weights of each criterion. Then, after detailed discussion of considerable information on each proposal, the project selection committee assigned a measure to each proposal for each criterion on a scale from 1 to 100 where higher is better.
Which proposal has the greatest unbiased weighted score based on the MCDM approach using the collected information from the RFPs?
A. Proposal A B. Proposal B C. Proposal C D. Proposal D E. Proposal E
Criteria | Weight | Proposal A | Proposal B | Proposal C | Proposal D | Proposal E |
C1. Technical approach | 40% | 40 | 90 | 40 | 80 | 40 |
C2. Management approach | 30% | 30 | 60 | 30 | 50 | 20 |
C3. Past performance | 20% | 50 | 20 | 20 | 40 | 10 |
C4. Price | 10% | 80 | 10 | 70 | 20 | 50 |
| Sum | 200 | 180 | 160 | 190 | 120 |