Question: Question 2. [Conduct Procurement, Vendor Selection] A project received proposals from a response to RFP and is in the decision process of selecting one vendor.

Question 2. [Conduct Procurement, Vendor Selection]

A project received proposals from a response to RFP and is in the decision process of selecting one vendor. The project selection committee agreed on the criteria and the weights of each criterion. Then, after detailed discussion of considerable information on each proposal, the project selection committee assigned a measure to each proposal for each criterion on a scale from 1 to 100 where higher is better.

Which proposal has the greatest unbiased weighted score based on the MCDM approach using the collected information from the RFPs?

A. Proposal A B. Proposal B C. Proposal C D. Proposal D E. Proposal E

Criteria

Weight

Proposal

A

Proposal

B

Proposal

C

Proposal

D

Proposal

E

C1. Technical approach

40% 40 90 40 80 40

C2. Management approach

30% 30 60 30 50 20

C3. Past performance

20% 50 20 20 40 10

C4. Price

10% 80 10 70 20 50

Sum 200 180 160 190 120

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!