Question: Question 2: Consider the following flow shop, F3//Cmax, scheduling problem 1 P1 4 P2 2 P3 5 dj 18 2 6 3 4 15 3

Question 2: Consider the following flow shop, F3//Cmax, scheduling problem 1 P1 4 P2 2 P3 5 dj 18 2 6 3 4 15 3 3 5 1 24 4 1 6 2 28 a) Construct a feasible schedule and evaluate it in terms of Cmax and Number of tardy jobs. b) Modify the schedule to obtain an improved schedule with respect to Cmax. Question 2: Consider the following flow shop, F3//Cmax, scheduling problem 1 P1 4 P2 2 P3 5 dj 18 2 6 3 4 15 3 3 5 1 24 4 1 6 2 28 a) Construct a feasible schedule and evaluate it in terms of Cmax and Number of tardy jobs. b) Modify the schedule to obtain an improved schedule with respect to Cmax
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts