Question: QUESTION 2 Crashing a network schedule works only when A complete risk assessment is performed The project team and the project manager agree on the

QUESTION 2
Crashing a network schedule works only when
A complete risk assessment is performed
The project team and the project manager agree on the course of action
It is the best alternative to overtime
Adding resources shortens activity durations