Question: Question 2 During project planning, you estimate the time needed for each activity and then add up the estimates to create the project estimate. You

Question 2
During project planning, you estimate the time needed for each activity and then add up the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?
The estimate is too long and should be created by management.
The team did not create the estimate and estimating takes too long using that method.
The project estimate should be the same as the customer's required completion date.
The team did not create the estimate, and a diagram was not used.
 Question 2 During project planning, you estimate the time needed for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!