Question: Question 2. Earned Value Analysis Perform an earned value analysis using the data in the table below. The project has a 12-month duration and a

Question 2. Earned Value Analysis Perform an
Question 2. Earned Value Analysis Perform an earned value analysis using the data in the table below. The project has a 12-month duration and a budget of 250,000. Data are provided for a project review after the first 6 months are completed. Activity January Feb March April May June Planned % Earned Value Completed Value Staffing 6,000 5,000 11,000 100% ? Blueprinting 3,000 6,000 9,000 100% ? Prototype 2,000 8,000 10,000 60% ? development Full Design 4,000 6,000 10,000 20,000 50% ? 7 ? ? Construction 2.000 35,000 37.000 15% Transfer 6,000 6,000 0% TOTAL ? Monthly plan 6,000 10,000 14,000 4,000 8,000 51,000 Monthly 6,000 12,000 15,000 4,000 10,000 52.000 Actual Using the formulas provided, calculate the following: a) Planned Value (PV) [1 mark] b) Earned Value (EV) [1 mark] c) Actual Cost (AC) [1 mark] d) Cost Variance (CV) [2 marks] e) Schedule Variance (SV) [2 marks] f) Cost Performance Index (CPI) [2 marks) 9) Schedule Performance Index (SPI) [2 marks] h) Budget at Completion (BAC) [1 mark] 1) Estimate at Completion (EAC) [2 marks] D) Estimate to complete (ETC) [2 marks] k) is the project on time and within budget? Justify your answers using the appropriate indicators above. (4 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!