Question: QUESTION 2 If a project has a net present value equal to zero, then On the project is not worth doing because it adds no
QUESTION 2 If a project has a net present value equal to zero, then On the project is not worth doing because it adds no value to shareholder wealth Ob any delay in receiving the projected cash inflows will cause the project's NPV to be negative Oc the initial cost of the project exceeds the present value of the project's subsequent cash flows d. the internal rate of return exceeds the discount rate On the discount rate exceeds the internal rate of return