Question 2: Job-Order Costing: Calculating unit product costs Custom Corporation uses a job-order costing system with a
Question:
Question 2: Job-Order Costing:
Calculating unit product costs Custom Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data:
Total machine-hours 20,000
Total fixed manufacturing overhead cost $80,000
Variable manufacturing overhead per machine-hour $3.00
Recently Job G215 was completed with the following characteristics:
Number of units in the job 40
Total machine-hours 70
Direct materials $910
Direct labor cost $3,600
Required:
a. Estimate the total manufacturing overhead cost. (4 marks)
b. Calculate the predetermined overhead rate for the year. (3 marks)
c. Calculate the amount of overhead applied to Job G215. (3 marks)
d. Calculate the total job cost for Job G215. (4 marks)
e. Calculate the unit product cost for Job G215. (3 marks)
f. Why do most companies use predetermined overhead rates rather than actual overhead rates? (3 marks)