Question: QUESTION 2 Kingston Processors Limited ( KPL ) constructed a solar plant on January 1 , 2 0 2 0 . The solar plant is
QUESTION
Kingston Processors Limited KPL constructed a solar plant on January The solar plant is estimated to have a useful life of years nil residual value from the date it was completed and ready to be used. The plant was operational on April but the entity actually commenced use of the plant on June The solar plant was selfconstructed and KPL incurred the following costs:
direct material, $ million
direct labour $ million
overheads $ million
Of the total overheads incurred, represents cost overruns due to inefficiencies by the project manager and $ represents general administrative overheads. To support with appropriate usage of the solar plant, the entity incurred an additional $ million to train all the operators to use the plant. The costs incurred in constructing the asset are expected to increase efficiencies and yield significant future economic benefits.
Required:
a Determine the depreciation charge for the period ended December marks
b Determine the carrying amount of the asset as at December marks
c Differentiate between capital and revenue expenditure giving an example of each from the scenario above marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
