Question: QUESTION 2 Kingston Processors Limited ( KPL ) constructed a solar plant on January 1 , 2 0 2 0 . The solar plant is

QUESTION 2
Kingston Processors Limited (KPL) constructed a solar plant on January 1,2020. The solar plant is estimated to have a useful life of 30 years (nil residual value) from the date it was completed and ready to be used. The plant was operational on April 1,2020, but the entity actually commenced use of the plant on June 30,2020. The solar plant was self-constructed and KPL incurred the following costs:
direct material, $600 million
direct labour $450 million
overheads $750 million
Of the total overheads incurred, 30% represents cost overruns due to inefficiencies by the project manager and $10,000,000 represents general administrative overheads. To support with appropriate usage of the solar plant, the entity incurred an additional $60 million to train all the operators to use the plant. The costs incurred in constructing the asset are expected to increase efficiencies and yield significant future economic benefits.
Required:
a) Determine the depreciation charge for the period ended December 31,2020.(2marks)
b) Determine the carrying amount of the asset as at December 31,2021.(4marks)
c) Differentiate between capital and revenue expenditure giving an example of each from the scenario above (5 marks)
QUESTION 2 Kingston Processors Limited ( KPL )

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!