Question 2: Manual Simulation (9 points)
Perform a manual simulation of a Bank Teller System with one teller and 4 customers coming in for service and wait in a single queue. The Time of Arrival (Clock time shown as minute) and Service Time (duration expressed in minutes) of the customers are given by the table below.
Customer Arrival and Service Times | Customer Number | Time of Arrival (@Minute) | Service Time (Minutes) |
| 1 | 0 | 3 |
| 2 | 2 | 3 |
| 3 | 5 | 1 |
| 4 | 8 | 2 |
Simulate the system for 10 minutes.
(1) Generate a record of simulation in a tabular format as that of Slide 35 of Lecture 4 Manual Simulation. (2) Generate two time plots, one for Number in System and the other for Teller Status. (3) Provide all statistics calculated from simulation results.
Slide 35 (for reference):
I'm sorry but this is all the information that I'm able to provide. Please answer whatever part you can, anything is fine
Complete Record of the Hand Simulation Statistical Accumulators Event Calendar Just-Finished Event Variables Entity Time Event No. t Type (t) BC) Attributes Amival Times: (In Queue In Service P N D 70 Q* B (Entity No., Time, Type] [1, 0.00, Am] 15.00, End] 0.00 Init 0 0 0 0 0 0.00 0.00 0.00 0.00 0.00 0 0.00 (1, [2. 1 0.00 Am 0 1 0 0.00 0 1 0.00 0.00 0.00 0.00 0.00 0 0.00 4.58, 6.84, 15.00 6.84, 15.00, Dep] Am] End Am] End) [2 1- 1 4.58 Dep 0 0 0 --- 1 1 0.00 0.00 4.58 4.58 0.00 0 4.58 [3, 2 6.84 Air 0 1 0 6.84 1 2 0.00 0.00 4.58 4.58 0.00 0 4.58 NON 3 9.24 Am 1 1 (9.24) 6.84 1 2 0.00 0.00 4.58 4.58 0.00 1 6.98 [2 [4, 1 [4, - 13 [5. 2 9.80 Dep 0 1 0 9.24 2 3 0.56 0.56 7.54 4.58 0.56 1 7.54 9.24 9.80, 15.00, 9.80 11.94, 15.00 11.94, 15.00, 15.66, 14.53, 15.00, 15.66, 15.00, 15.26, 15.66, 15.26, 15.66, Am] Dep) End] Dep] An) End] Am] End] Depl Am] End] Dep) End) Am] Depl Am] Dep] 4 11.94 Am 1 1 (11.94) 9.24 2 3 0.56 0.56 7.54 4.58 0.56 1 9.68 5 14.53 Am 2 1 (14.53, 11.94) 9.24 2 3 0.56 0.56 7.54 4.58 3.15 N 12.27 3 - [6, 13, [6, [3 15.00 End 2 1 (14.53, 11.94) 9.24 2 3 0.56 0.56 7.54 4.58 4.09 N 12.74 Simulation with Arena - Fundamental Simulation Concepts C2/35 Complete Record of the Hand Simulation Statistical Accumulators Event Calendar Just-Finished Event Variables Entity Time Event No. t Type (t) BC) Attributes Amival Times: (In Queue In Service P N D 70 Q* B (Entity No., Time, Type] [1, 0.00, Am] 15.00, End] 0.00 Init 0 0 0 0 0 0.00 0.00 0.00 0.00 0.00 0 0.00 (1, [2. 1 0.00 Am 0 1 0 0.00 0 1 0.00 0.00 0.00 0.00 0.00 0 0.00 4.58, 6.84, 15.00 6.84, 15.00, Dep] Am] End Am] End) [2 1- 1 4.58 Dep 0 0 0 --- 1 1 0.00 0.00 4.58 4.58 0.00 0 4.58 [3, 2 6.84 Air 0 1 0 6.84 1 2 0.00 0.00 4.58 4.58 0.00 0 4.58 NON 3 9.24 Am 1 1 (9.24) 6.84 1 2 0.00 0.00 4.58 4.58 0.00 1 6.98 [2 [4, 1 [4, - 13 [5. 2 9.80 Dep 0 1 0 9.24 2 3 0.56 0.56 7.54 4.58 0.56 1 7.54 9.24 9.80, 15.00, 9.80 11.94, 15.00 11.94, 15.00, 15.66, 14.53, 15.00, 15.66, 15.00, 15.26, 15.66, 15.26, 15.66, Am] Dep) End] Dep] An) End] Am] End] Depl Am] End] Dep) End) Am] Depl Am] Dep] 4 11.94 Am 1 1 (11.94) 9.24 2 3 0.56 0.56 7.54 4.58 0.56 1 9.68 5 14.53 Am 2 1 (14.53, 11.94) 9.24 2 3 0.56 0.56 7.54 4.58 3.15 N 12.27 3 - [6, 13, [6, [3 15.00 End 2 1 (14.53, 11.94) 9.24 2 3 0.56 0.56 7.54 4.58 4.09 N 12.74 Simulation with Arena - Fundamental Simulation Concepts C2/35