Question: QUESTION 2 Masulis Inc. is considering a project that has the following cash flow and WACC data. What is the project's discounted payback? WACC: Year

QUESTION 2 Masulis Inc. is considering a project that has the following cash flow and WACC data. What is the project's discounted payback? WACC: Year 10.00% 0 -$1,225 1 $525 2 $485 3 $445 4 $405 Cash flows O a. 2.92 O b. 3.50 O c. 3.62 O d.3.78 O e. 3.05 years years years years years