Question: Question 2. Material Requirements Planning (35 marks) Week 1 2 3 4 5 6 7 8 9 10 Gross requirements 40 50 20 10 30
Question 2. Material Requirements Planning (35 marks)
|
| Week | |||||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross requirements | 40 | 50 | 20 | 10 | 30 | 80 | 70 | 60 | 100 | 20 |
The MRP gross requirements for product A in the next 10 weeks are shown in the following table. The lead time for A is three weeks, and the setup cost is $300. The carrying cost is $2 per unit per week. Suppose the initial inventory at the beginning of week 1 is 150 units.
Questions:
(1) Determine for what quantity the order should be planned to be received for each week using the following three lot-sizing methods: lot-for-lot, least total costs, and least unit cost. (Hint: start from the week when the initial inventory is insufficient to satisfy the gross requirements).
| Lot for lot | Week | |||||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Planned order receipts |
|
|
|
|
|
|
|
|
|
|
| Least Total Costs | Week | |||||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Planned order receipts |
|
|
|
|
|
|
|
|
|
|
| Least Unit Cost | Week | |||||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Planned order receipts |
|
|
|
|
|
|
|
|
|
|