Question: QUESTION 2 : ( Must use the given Template on next page and it must be typed, No alteration allowed ) [ DO NOT Include

QUESTION 2:
(Must use the given Template on next page and it must be typed, No alteration allowed)[DO NOT Include this network in the solution]
Note: Time units are in weeks.
(a) How many minimum resources are required to execute the above schedule as it is, without any resource constraint?
Task 0123456789101112131415161718192021222324252627282930313233
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
Total Resources
(b) Refer to the network on the previous page; construct the resource loading schedule when only eight resources are available. Use Minimum slack, smallest duration, lowest ID heuristic. (Do not split the activities)
(Must use this given Template BELOW and it must be typed, dont change the font)
Task 0123456789101112131415161718192021222324252627282930313233
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
Resources Scheduled
Resources Available
(c) List the order in which you scheduled the activities of the project.
(d) What is the project completion time after loading all the resource? ______________
(e) After loading all activities in part b, state ONLY non-zero slacks for the activities.
Activity A B C D E F G H I J K L M N O P Q R
Slack

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!