Question: QUESTION 2 : ( Must use the given Template on next page and it must be typed, No alteration allowed ) [ DO NOT Include
QUESTION :
Must use the given Template on next page and it must be typed, No alteration allowedDO NOT Include this network in the solution
Note: Time units are in weeks.
a How many minimum resources are required to execute the above schedule as it is without any resource constraint?
Task
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
Total Resources
b Refer to the network on the previous page; construct the resource loading schedule when only eight resources are available. Use Minimum slack, smallest duration, lowest ID heuristic. Do not split the activities
Must use this given Template BELOW and it must be typed, dont change the font
Task
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
Resources Scheduled
Resources Available
c List the order in which you scheduled the activities of the project.
d What is the project completion time after loading all the resource?
e After loading all activities in part b state ONLY nonzero slacks for the activities.
Activity A B C D E F G H I J K L M N O P Q R
Slack
Step by Step Solution
There are 3 Steps involved in it