Question: Question 2 of 28 - /3.1 E View Policies Current Attempt in Progress Sheridan Company is constructing a building. Construction began in 2020 and the

 Question 2 of 28 - /3.1 E View Policies Current Attempt

Question 2 of 28 - /3.1 E View Policies Current Attempt in Progress Sheridan Company is constructing a building. Construction began in 2020 and the building was completed 12/31/20. Sheridan made payments to the construction company of $3084000 on 7/1, $6396000 on 9/1, and $5900000 on 12/31. Weighted-average accumulated expenditures were O $3674000. O $9480000. O $15380000. O $3141000