Question: Question 2 of 3 Help with solution 8 . 8 9 2 0 Current Attempt in Progress Your answer is partially correct. Inexperienced construction company

Question 2 of 3
Help with solution
8.8920
Current Attempt in Progress
Your answer is partially correct.
Inexperienced construction company Concord Corp. signed a risky non-cancellable contract to build a research facility at a fixed contract amount of $2,200,000. The work began in early 2020 and Concord incurred costs of $990,000. At December 31,2020, the estimated future costs to complete the project totalled $990,000. During 2021, Concord ran into trouble with weather conditions and incurred the expected costs of $990,000 and estimated that it would need to spend an additional $365,000 to complete the project. During 2022, Concord reluctantly completed the project, incurring further costs of $390,000.
Calculate the amount of gross profit or loss that should be recognized each year under the percentage-of-completion method. (Enter negative amounts using either a negative sign preceding the number e.g.-45 or parentheses e.g.(45). Round percent complete to 2 decimal places, e.g.15.25.)
\table[[,December 31,2020,December 31,2021,December 31,2022],[Gross profit /(loss),$,110000,$,$]]
Prepare the December 31,2021 year-end journal entry to record costs, revenues, expenses, and losses from the contract. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. Round percent complete to 2 decimal places, e.g.15.25.)
Date
December 31,
2021
Construction Expenses
Contract Asset/Liability
Revenue from Long-Term Contracts
Account Titles and Explanation
Debit
Credit
eTextbook and Media
Assistance Used
Solution
Assistance UsedQuestion 2 of 3
8.8920
Current Attempt in Progress
Your answer is partially correct.
Inexperienced construction company Concord Corp. signed a risky non-cancellable contract to build a research facility at a fixed contract amount of $2,200,000. The work began in early 2020 and Concord incurred costs of $990,000. At December 31,2020, the estimated future costs to complete the project totalled $990,000. During 2021, Concord ran into trouble with weather conditions and incurred the expected costs of $990,000 and estimated that it would need to spend an additional $365,000 to complete the project. During 2022, Concord reluctantly completed the project, incurring further costs of $390,000.
Calculate the amount of gross profit or loss that should be recognized each year under the percentage-of-completion method. (Enter negative amounts using either a negative sign preceding the number e.g.-45 or parentheses e.g.(45). Round percent complete to 2 decimal places, e.g.15.25.)
\table[[,December 31,2020,December 31,2021,December 31,2022],[Gross profit/(loss),$,$,$
Question 2 of 3 Help with solution 8 . 8 9 2 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!