Question: Question 2 of 4 0 2 Points You are preparing your project report and you want to understand your cost efficiency. Which formula should you

Question 2 of 40
2 Points
You are preparing your project report and you want to understand your cost efficiency. Which formula should you use?
Est preparando el informe de su proyecto y desea comprender la eficiencia a nivel de costos. Qu frmula debe usar?
Select the correct response:
CPI
SV
SPI
CV