Question: QUESTION 2 only please QUESTION 1 Using a project of your choice describe a WBS and construct the WBS for your project to at least

QUESTION 2 only please
QUESTION 1 Using a project of your choice describe a WBS and construct the WBS for your project to at least 4 levels. (20) QUESTION 2 The following information is provided for the activities in a building project: Activity Immediate Predecessors) Time Iweeks) Cost R 2 200 A TASE 4 B 500 2 A 200 D B 5 600 E 2 300 F CE 7 800 G D 2 300 H F G 5 400 2.1 Draw the AON diagram for the project tabulating the forward pass, backward pass and the lack times of each activity (15) What is the completion time for the project? (2) What is the cost of completing the project? 13) 2.2 23 QUESTION 3 (20)Step by Step Solution