Question: Question 2 Please create an activity network diagram for the following activity table and answer the questions. The duration of this project is weeks. The

Question 2
Please create an activity network diagram for the following activity table and answer the questions.
The duration of this project is
weeks. The activity
has the second highest slack time of all the activities.
The project manager is not happy with the plan and decides to complete activity G one week earlier and activity J three weeks earlier. The overall project duration is
reduced by
weeks. The project manager still wants to reduce the duration further. He has three options:
A - Remove dependency of G on E
B- Dependency of M on H
C - Dependency of J on I
D - Dependency of F on E
The best option is
 Question 2 Please create an activity network diagram for the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!