Question: Question 2 Please create an activity network diagram for the following activity table and answer the questions. The duration of this project is weeks. The
Question
Please create an activity network diagram for the following activity table and answer the questions.
The duration of this project is
weeks. The activity
has the second highest slack time of all the activities.
The project manager is not happy with the plan and decides to complete activity G one week earlier and activity J three weeks earlier. The overall project duration is
reduced by
weeks. The project manager still wants to reduce the duration further. He has three options:
A Remove dependency of on
Dependency of M on H
C Dependency of J on I
D Dependency of F on E
The best option is