Question: Question 2: Resolving resource conflicts Study the table given below to answer the question. Find out which resources have been over allocated in the project.

Question 2: Resolving resource conflicts Study the table given below to answer the question. Find out which resources have been over allocated in the project. The activities begin on early start times and would require resources as shown in the table. Use 8 hours per day for each worker. Show appropriate chart with over allocation resources. (10 marks) Predecessor Resource A B Activity Activity Length A 9 B 8 13 D 11 E 6 F 9 G 9 H 9 M 9 J 4 K 1 L 11 B D E F, G F,H M, K Sam Twinkle Jack Twinkle Jack Sam Jack Sam Twinkle Sam Twinkle Jack Resource Hours Per Day 1 7 6 6 4 4 5 6 7 2 6 7
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
