Question: QUESTION 2 The contractor building a large hotel complex considers installing a 1 2 5 kW three fase generator to provide power during the construction

QUESTION 2
The contractor building a large hotel complex considers installing a 125kW three fase generator to provide power during the construction of the entire project. The generator will cost R 98000(VAT included) and is expected to have a life of 4 years with R25000 resale value at the end of its useful life. The fixed operating costs and maintenance of the equipment will amount to R15345 per year independent of the extent of use plus a fuel and variable operating cost of R291(VAT Excluded) per day of use. The manager of an adjacent garage offers to provide the necessary power from their 250kW (three Phase) generator at a fixed, all-inclusive cost of R1287,75(VAT included) per day of use. If the contractor's cost of capital equals 12%:
1. Calculate by break-even analysis the number of days per year on which power would have to be provided to make the external source of power (125KW Generator) the cheaper alternative.
2. What would the contractor's cost of capital have to be for the two power sources to be of equal cost assuming a power requirement for 50 daysoftheyear?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!