Question: QUESTION 2 The contractor building a large hotel complex considers installing a 1 2 5 kW three fase generator to provide power during the construction
QUESTION
The contractor building a large hotel complex considers installing a kW three fase generator to provide power during the construction of the entire project. The generator will cost R VAT included and is expected to have a life of years with R resale value at the end of its useful life. The fixed operating costs and maintenance of the equipment will amount to R per year independent of the extent of use plus a fuel and variable operating cost of RVAT Excluded per day of use. The manager of an adjacent garage offers to provide the necessary power from their kW three Phase generator at a fixed, allinclusive cost of RVAT included per day of use. If the contractor's cost of capital equals :
Calculate by breakeven analysis the number of days per year on which power would have to be provided to make the external source of power KW Generator the cheaper alternative.
What would the contractor's cost of capital have to be for the two power sources to be of equal cost assuming a power requirement for daysoftheyear
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
