Question: Question 2 . The daily demand for a spare engine part is a random variable whose distribution,based on past experience, is given below: The parts
Question The daily demand for a spare engine part is a random variable whose distribution,based on past experience, is given below:
The parts cost $ each and $ each when purchased on an emergency basis. Unused parts can be scrapped for of their purchase price.
Part A How many parts should be acquired to maximize expected profit?
Note: Even though the setting described here is not exactly the standard newsvendor problem with revenue and salvage value, the same concept of underage shortage and overage excess costs apply; you just need to derive these costs with the parameters described in this problem.
Part B Now suppose the planning horizon is over days with only one purchase opportunity in advance of the day period and the daily demand following the same distribution as before. Assume demands from one day to the next are independent. The part is expected to be obsolete after days with the same salvage value as in part A Other cost parameters are the same as in Part A as well. Furthermore, holding costs for unused parts are based on a daily interest rate of
Using critical ratio, how many parts should be acquired in advance of the day period?
Note: You may use the Central Limit Theorem to approximate the demand over days with a normal distribution.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock