Question: Question 2: The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in

Question 2: The day when the order arrived,

Question 2: The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Order Due Date (days from now) Time Since Order Arrived (days ago) 13 15 17 Processing Time (days) 12 10 10 A B 36 40 39 Due date is 41; D 22 8 E 24 14 45 Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due days. Make a comment. (30P)