Question: Question 2 The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates xed


Question 2 The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates xed overhead costs at a standard rate of $19 per direct labour hour. Direct labour: Standard cost is 5 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6 720 F Fixed overhead costs: Estimated: $60 000 Actual: $58 720 Required (a) How many actual labour hours were worked to produce the 18 000 tiles? (b) What is the price variance for direct labour? (c) What is the budget variance for xed costs
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
