Question: Question 2 The meeting notes state that training will happen in two phases one for managers and one for staff. Which of the following three

Question 2
The meeting notes state that training will happen in two phasesone for managers and one for staff. Which of the following three-point time estimates would you choose for fully training the team (including planning, training the managers, and training the staff at each location)?
Status: [object Object]
1 point
Optimistic: 10 days; Most Likely: 14 days; Pessimistic: 21 days
Optimistic: 20 days; Most Likely: 14 days; Pessimistic: 10 days
Optimistic: 2 days; Most Likely: 1 day; Pessimistic: 4 days
Optimistic: 15 days; Most Likely: 30 days; Pessimistic: 45 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!