Question: QUESTION 2 The project kicked off during the summer and many stakeholders and team members will be out on vacation in the next few weeks.

QUESTION 2 The project kicked off during the

QUESTION 2 The project kicked off during the summer and many stakeholders and team members will be out on vacation in the next few weeks. You realize it will take you at least 6 weeks to get all key people in a conference room to do a risk identification exercise. What tool(s) can you use which don't require face to face interaction with people to get a head start on identifying risks? Check all that apply. Delphi Technique Plan Evaluation Risk Register Documentation Review Analogy Comparisons