Question: Question 2 (Total 20 marks) Yat Ching Co. is an authorised company to do the packing of Nissin Instant Noodles for supplying private hospitals in
Question 2 (Total 20 marks)
Yat Ching Co. is an authorised company to do the packing of Nissin Instant Noodles for supplying private hospitals in Hong Kong. Yat Ching Co. mainly packs two products, namely a) individual pack , and b) bulk pack
For an individual pack, one piece of finished product will require 1 noodle base, 1 seasoning powder aluminum bag, 1 sesame oil sachet, and 1 outside plastic pocket
While for a piece of bulk pack product, there needs 6 noodle bases and one bigger outside plastic pocket (no seasoning powder or sesame oil required) The Bill of Materials for both packing versions can be referred as follows:
The following is the Master Production Schedule (MPS) data of both products as well as the lot size, lead time, safety stock requirement and the minimum order quantity for the Noodle Base. Please also note the scheduled receipt and projected on hand status.
MRP worksheet
| Lead Time: 1 week | ||||||||
| Week number | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Gross Requirements |
|
| 400 | 600 |
| 400 | 600 |
| |
| Planned order releases |
| 400 | 600 |
| 400 | 600 |
|
| |
| Lead Time: 1 week | ||||||||
| Week number | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Gross Requirements |
|
|
|
| 70 | 90 |
| 40 | |
| Planned order releases |
|
|
| 70 | 90 |
| 40 |
| |
| Part name: Noodle Base |
|
|
|
| Lot size: | L4L |
| ||||
| Minimum order quantity: | 100 | units |
|
| Lead time: | 1 | week | ||||
| Immediate Parent(s): 1 per Ind. Pack and 6 per Bulk pack |
| Safety stock: | 100 | units | |||||||
| Week number |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Gross Requirements |
|
|
|
|
|
|
|
| |||
| Scheduled Receipts |
|
|
|
| 1000 |
|
|
| |||
| Projected on hand | 200 |
|
|
|
|
|
|
|
| ||
| Net Requirements |
|
|
|
|
|
|
|
|
| ||
| Planned order receipts |
|
|
|
|
|
|
|
|
| ||
| Planned order releases |
|
|
|
|
|
|
|
| |||
- Complete the MRP sheet regarding only the Noodle Base and enter the final answers in the following table. (7 marks)
(Tips: you may like to use the above worksheet to do the MRP calculations and then copy the last line results to this table)
| Week No. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Planned Order Release |
|
|
|
|
|
|
| 0 |