Question: Question 2 Under a contract for a hospital extension, the contractor is six weeks past the completion date ( with no valid excuses ) when

Question 2
Under a contract for a hospital extension, the contractor is six weeks past the completion date (with
no valid excuses) when the architect issues an instruction requiring extra work which will take a week
to carry out.
Explain the contractor's rights (if any) to an extension of time or financial compensation for direct loss
and/or expense incurred, stating any assumptions you make about the precise wording of the
contract.
Would your answer be different if, instead of the architect's instruction, the contractor had been
delayed for the extra week by exceptionally bad weather?
Total marks]
Question 3
Discuss the contractor's rights to be paid for construction work, showing how the amount to be paid is
arrived at, and remunerated to the contractor, and how it may be changed within the terms of a
standard-form construction contract with which you are familiar.
Total [20 marks]
Question 2 Under a contract for a hospital

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!