Question: Question 2 Under a contract for a hospital extension, the contractor is six weeks past the completion date ( with no valid excuses ) when
Question
Under a contract for a hospital extension, the contractor is six weeks past the completion date with
no valid excuses when the architect issues an instruction requiring extra work which will take a week
to carry out.
Explain the contractor's rights if any to an extension of time or financial compensation for direct loss
andor expense incurred, stating any assumptions you make about the precise wording of the
contract.
Would your answer be different if instead of the architect's instruction, the contractor had been
delayed for the extra week by exceptionally bad weather?
Total marks
Question
Discuss the contractor's rights to be paid for construction work, showing how the amount to be paid is
arrived at and remunerated to the contractor, and how it may be changed within the terms of a
standardform construction contract with which you are familiar.
Total marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
