Question: QUESTION 2. Use the Normal time given in Table 2 to reduce the project by 8 days. What is the total added cost? Show the
QUESTION 2.
Use the Normal time given in Table 2 to reduce the project by 8 days. What is the total added cost? Show the activity/activities that need to crash for each day. For example, what activity to crash for day 1, what activity to crash for day 2, and so forth.
| TABLE 2
|
|
| Time (days) | Activity cost (S) | |||
| Activity | Description | Predecessor | Normal | Crash | Normal | Crash | |
| A | Excavation, pour footers | none | 6 | 4 | $10 | 20 | |
| B | Lay foundation | A | 5 | 3 | $22 | 28 | |
| C | Frame and roof | B | 5 | 4 | $15 | 22 | |
| E | Sewer (floor) drains | B | 3 | 2 | $21 | 25 | |
| F | Install insulation | C | 5 | 4 | $25 | 30 | |
| G | Pour basement floor | E | 5 | 3 | $12 | 18 | |
| I | Install windows | F | 4 | 3 | $20 | 22 | |
| J | Rough electrical wiring | F | 3 | 2 | $20 | 20 | |
| K | Install furnace | C,G | 8 | 5 | $11 | 23 | |
| L | Exterior brickwork | I | 8 | 6 | $16 | 28 | |
| M | Install plasterboard | J,K | 10 | 8 | $18 | 26 | |
| N | Roof shingles | L | 4 | 3 | $23 | 29 | |
| O | Attach gutter | N | 5 | 2 | $25 | 31 | |
| P | Grading | O | 7 | 3 | $12 | 16 | |
| Q | Lay subflooring | M | 5 | 4 | $17 | 22 | |
| R | Lay driveway | P | 8 | 6 | $20 | 30 | |
| T | Kitchen, sink, appliances | Q | 8 | 4 | $18 | 28 | |
| V | Painting | T | 8 | 6 | $15 | 24 | |
| W | Finish wood floor | V | 8 | 6 | $25 | 34 | |