Question: Question 2 Using the information presented in the following table, answer the following questions. ( Hint : First determine the total job time for each
Question 2
Using the information presented in the following table, answer the following questions. (Hint: First determine the total job time for each job by calculating the total processing time for the job and then adding in the setup time. All times are in hours.)
| Job | Processing Time (hr) per Unit | Units per Job | Setup Time (hr) | Due Hour |
| a | 0.14 | 45 | 0.7 | 4 |
| b | 0.25 | 14 | 0.5 | 10 |
| c | 0.10 | 18 | 0.2 | 12 |
| d | 0.25 | 40 | 1.0 | 20 |
| e | 0.10 | 75 | 0.5 | 15 |
a. Identify the processing sequence that would result using priority rules.
| Rule | Sequence |
| MST | (Click to select) d-e-b-a-c c-d-e-b-a a-b-e-d-c b-d-e-c-a |
| SPT | (Click to select) c-b-a-e-d c-d-e-b-a d-e-b-a-c b-d-e-c-a |
| EDD | (Click to select) a-b-c-e-d c-d-e-b-a d-e-b-a-c b-d-e-c-a |
| CR | (Click to select) a-d-e-b-c c-d-e-b-a d-e-b-a-c b-d-e-c-a |
b. For each priority rule, determine (1) average flow time, (2) average hours late, and (3) average WIP. (Round the final answers to 2 decimal places.)
| MST | SPT | EDD | CR | |
| Average flow time | ||||
| Average hours late | ||||
| Average WIP | ||||
c. Is one priority rule superior to the others?
-
Yes
-
No
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
