Question: Question 2 Using the information presented in the following table, answer the following questions. ( Hint : First determine the total job time for each

Question 2

Using the information presented in the following table, answer the following questions. (Hint: First determine the total job time for each job by calculating the total processing time for the job and then adding in the setup time. All times are in hours.)

Job Processing Time (hr) per Unit Units per Job Setup Time (hr) Due Hour
a 0.14 45 0.7 4
b 0.25 14 0.5 10
c 0.10 18 0.2 12
d 0.25 40 1.0 20
e 0.10 75 0.5 15

a. Identify the processing sequence that would result using priority rules.

Rule Sequence
MST (Click to select) d-e-b-a-c c-d-e-b-a a-b-e-d-c b-d-e-c-a
SPT (Click to select) c-b-a-e-d c-d-e-b-a d-e-b-a-c b-d-e-c-a
EDD (Click to select) a-b-c-e-d c-d-e-b-a d-e-b-a-c b-d-e-c-a
CR (Click to select) a-d-e-b-c c-d-e-b-a d-e-b-a-c b-d-e-c-a

b. For each priority rule, determine (1) average flow time, (2) average hours late, and (3) average WIP. (Round the final answers to 2 decimal places.)

MST SPT EDD CR
Average flow time
Average hours late
Average WIP

c. Is one priority rule superior to the others?

  • Yes

  • No

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!