Question: Question 20 Which statement is not correct regarding the forward pass calculations and its algorithm? The late finish timing is passed to the successor
Question 20 Which statement is not correct regarding the forward pass calculations and its algorithm? The late finish timing is "passed" to the successor activities. The early finish timing is "passed" to the successor activities. Duration is added to the early start to calculate the early finish. The early finish timing is the early start timing of the successor activities. 3 pts
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
