Question: Question 20 Which statement is not correct regarding the forward pass calculations and its algorithm? The late finish timing is passed to the successor

Question 20 Which statement is not correct regarding the forward pass calculations

Question 20 Which statement is not correct regarding the forward pass calculations and its algorithm? The late finish timing is "passed" to the successor activities. The early finish timing is "passed" to the successor activities. Duration is added to the early start to calculate the early finish. The early finish timing is the early start timing of the successor activities. 3 pts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!